Energy Analyst Kwadwo Poku has warned that Ghana’s current power challenges could persist for at least two years, blaming inadequate investment in electricity transmission infrastructure over the past two years.

He says the country is unlikely to overcome the difficulties in the immediate future, even if the government releases funding for new transmission projects, because of the time required to award contracts and complete the necessary infrastructure.

Speaking on JoyNews’ Newsfile on Saturday, November 28, Mr Poku said the lack of investment in the transmission network had contributed to the current situation and would continue to affect the reliability of electricity supply.

“The problem is the lack of investment in the last two years in the transmission,” he said.

He stressed that the challenges would not be resolved quickly, predicting that the country would have to contend with them for another two years.

“Immediately, we are going to have this problem for the next two years. Two years,” he said.

Emphasising his confidence in the prediction, Mr Poku described himself as an oracle and insisted that he was certain about his assessment.

Mr Poku’s assessment comes as the government makes provision for investment in the transmission sector in the 2027 Budget.

He referred to an allocation of 500 million announced by the Energy Minister for transmission infrastructure under the new economy, but questioned how soon the funding would translate into completed projects and improved electricity supply.

He argued that the proposed investment would not address the immediate challenges, given the lengthy process involved in developing transmission infrastructure.

“Today, if you’re going to give money to GRIDCo in 2027, how long do you think something will take?” he asked.

Mr Poku also questioned the government’s decision to cancel an agreement with German development bank KfW, as well as the delay in acting on a 50 million World Bank funding arrangement intended for the transmission sector.

He said the government had inherited two agreements when it assumed office in January 2025, but the cancellation of the KfW arrangement had raised concerns about the availability of funding for the required projects.

He further questioned why the World Bank funding had not been acted upon, arguing that the country could not afford further delays in addressing gaps in the transmission network.

To demonstrate the time required to complete such projects, Mr Poku cited the K1 and K2 transmission lines, which he said were awarded in July 2024 but were still undergoing work.

The projects involve the Anwomaso–Ahodwo transmission line, which he said had yet to be fully completed despite the contract having been awarded more than two years ago.

He said the timeline for the K1 and K2 projects showed why the government should not expect transmission improvements to happen immediately after announcing new funding.

“We awarded the K1 and K2 they are talking about in July 2024. You are talking about a shutdown three days ago to now operationalise that line,” he said.

Mr Poku maintained that even if the government made fresh funding available to GRIDCo, the process of developing and completing transmission lines would take considerable time.

He therefore cautioned against expectations that the current power challenges would be resolved in the short term, insisting that the effects of the limited investment in transmission would continue to be felt over the next two years.

He said addressing the situation would require sustained investment and timely implementation of transmission projects, rather than relying solely on budgetary allocations.

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.

DISCLAIMER: The Views, Comments, Opinions, Contributions and Statements made by Readers and Contributors on this platform do not necessarily represent the views or policy of Multimedia Group Limited.



Source link
Share.
Exit mobile version