Six major drainage improvement works under the Greater Accra Resilient and Integrated Development (GARID) project are awaiting financial authorisation from the Ministry of Finance before contracts can be awarded and construction works commence, the Minister of Works, Housing and Water Resources, Mr Ahmed Ibrahim, has disclosed.
The projects, which are currently at the tendering and contract award stage, include the reconstruction of the Abbosey Okai Bridge, construction of the Atomic East and West detention ponds, improvement works on the Alajo drain, repackaging of improvement works on the Nima drain, and installation of Accra Flood Early Warning Systems.
Mr Ibrahim said the implementation of the drainage improvement works was subject to the granting of the required commitment authorisation by the Ministry of Finance.
He made this known when he mounted the dispatch box in Parliament to respond to questions from Members of Parliament on the current state of the GARID project.
Mr Ibrahim said the project was implementing both structural and non-structural flood mitigation measures, using a basin-wide approach focused on the Odaw Basin.
On the Nima-Paloma drainage works, he said the contract had been terminated, adding that the project would be repackaged and re-awarded to a new contractor, subject to the necessary commitment authorisation from the Ministry of Finance.
He said at the time of termination, progress of work on the project stood at 13 per cent for evacuation works, 25 per cent for the demolition of the existing drain, 9.7 per cent for casting of the concrete base and 9.5 per cent for casting of concrete walls.
Mr Ibrahim said the Ministry had engaged Messrs Dredge Masters to desilt the Nima-Paloma drain to improve the conveyance of run-off water while awaiting the financial authorisation.
“Further, some additional local measures were put in place to reduce the exposure of adjoining communities at the upstream and downstream sections of the Nima drain where the previous contractor had initiated works but had not completed,” he said.
He added that the Ministry was engaging relevant stakeholders, including the World Bank, to determine the most appropriate procurement arrangement for securing a new contractor to return to the site and complete the project.
The GARID project is a major World Bank-funded initiative aimed at addressing perennial flooding, poor solid waste management and climate vulnerability in the Greater Accra Region.
BY BENJAMIN ARCTON-TETTEY